Regional Directorate Quetta has made untiring efforts to meet the milestones as set out in the PC-I of the project. Site development in PIFRA Replication phase is in progress. The site development at DAO Sibbi, DAO Qilla Abdullah and DAO Dhadar has been completed, while, super structure at DAO Mustung and DAO Pishin has also been completed. Moreover, site preparation at DAO Kalat has been re-initiated after slack season on 15th of March 2008 and expected to be completed by 15 June 2008. Bidding process has been completed on 22nd of March, 2008 for 4 new upcoming sites included DAOs Noshki, Khuzdar, Dera Allah Yar and Turbat.The assignment to upload the historical data of GP fund and pension of the employees of Quetta from manual record to SAP/R3 system is expected to be completed by June 30, 2008. AG office Balochistan has up till now recorded data of 5501 pensioners on SAP/R3 while AGPR sub-office Quetta has recorded 8522 cases of pensioners and GP fund to date.Training on SAP/R3, FI and HR were conducted at Field Office Training Center (FOTC), AG office Balochistan for all the staff of developed sites. Training in Audit was also conducted at the office of DG Provincial Audit Quetta.